Nightworks Disruption details -November – Feb 2020 Chilworth Station platform lengthening

Network Rail have forewarned that they will be carrying out night time works on Platform 2 of Chilworth station from 19 November – 2 February 2020.

They will be part demolishing the existing platform, rebuilding and lengthening it, in preparation for accommodating 4 carriage trains in the future.

Plant and machinery will be stored on the island by the bus stop.

Full details are –

November

Tues 18 – Fri 22    00.05 hrs – 4.30       Platform ramp demolition

Sun 24 – Mon 25   1 am – 4am               Platform ramp extension

December

Sun 8 Dec – Friday 13   00;55 – 5.05     Platform ramp extension

Tues 17 Dec- Fri 20       00.35 – 5.10      Platform ramp extension

January 2020

Tues 7 Jan – Fri 10         00.35 – 5.10      Platform ramp extension

Tues 14 – Fri 17               00.35 – 5.10      Platform ramp extension

Thurs 23 – Fri 24            00.35 – 5.10      Platform ramp extension

Tues 28 – Thur 30         00.35 – 5.10      Platform ramp extension

February 2020

Mon 3 – Fri 7                   00.35 – 5.10      Platform ramp extension

Network Rail apologise for the disruption.

National helpline number is 03457 11 41 41

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s